雷尼尔海滩高中 Replacement Project
The existing 雷尼尔海滩高中 will be replaced with a new high school building on the same site. The construction will be done in phases so the school can remain on campus during the project.
You can contact SPS in your own language through the online feedback form
时间轴
- 预设计阶段完成
- 方案设计阶段完成
- 设计开发阶段完成
- Construction documents/permitting phase in progress
- 投标和授予阶段完成
- Phased construction: April 2022-December 2026
- 第三期工程正在进行
- Estimated move into western 70% of new building: January 2025
- Phase 4, construction of Performing Arts building expected completion June 2026
- Phase 5, field installation expected completion December 2026.
项目进展
Progress updates are posted for the previous month.
2024年2月的主要活动
- 钢结构安装完成.
- Completed concrete slabs on metal decks.
- Continued to install roofs on the main classroom building and gymnasium.
- 延续外墙框架, 防火, 内部轻计螺柱安置, 绝缘, 机械, 电, 和管道(MEP)安装.
Major activity planned for March 2024
- Begin window placement and continue masonry around building perimeter.
- Continue exterior metal stud framing, sheathing, and waterproofing on the classroom building.
- 继续防火工作.
- Continue interior light gauge metal stud framing, 绝缘, and wallboard installation.
- Continue roofing work on the main classroom building and gymnasium.
- 继续MEP和洒水车粗修.
Live Webcams and 项目进展 Photos
View the webcams to see the project live.
This slide show shows the project as it proceeds.
社区参与
学校设计谘询小组(SDAT)
在设计过程的早期, representatives from the school community come together to form a school’s SDAT. SDATs typically include school and district staff, parents, students, and community members. The project construction managers also take part. Due to the timing of the 雷尼尔山海滩 SDAT, meetings were held virtually. Read more and review the meeting minutes.
A virtual community update about the 雷尼尔海滩高中 project was held on June 16.
项目设计
Architects renderings of the new school
项目简介
雷尼尔海滩高中 will be replaced with a new four-story high school of approximately 297,000平方英尺. When completed, it will provide permanent space for 1,600 students grades 9-12. Students will remain on-site during the phased construction. A regional 技术中心 is being incorporated into the project as well as a district data center. The project is being built with aspirations of a LEED Platinum certification.
设计公司: 巴塞蒂建筑事务所/穆迪·诺兰
项目管理公司: 拟基本解
总承包商: Lydig施工
项目预算: $238.2M
资金来源: Funded by the Building Excellence V Capital Levy (BEX V), approved by Seattle voters in 2019 and the Buildings, 技术, and 学者/Athletics V Capital Levy (BTA V), 由西雅图选民于2022年批准.