Montlake

Montlake 小学 Modernization and Addition Project

现有的学校建筑将进行现代化改造,并将增建一座.

Montlake 小学 has moved to the John 3月shall School interim site, 东拉文纳大道520号, for the 2023-24 and 2024-25 school years.

建设阶段图形显示学校正处于建设阶段
Learn what happens during these project phases

时间轴

  • 预设计阶段完成
  • 方案设计完成
  • Design development phase complete
  • Construction documents/permitting phase in progress
  • 投标和授予阶段完成
  • 施工中
  • 学校于2025年秋季开学

项目进展

Milestone Reached — 前ping Out Ceremony

将最后一根梁放在钢结构上被称为新建筑的“顶部”. 蒙特莱克小学新校舍的封顶仪式于周四举行, 3月. 7, 2024. 照片和视频如下.

2 people stand on a steel-framed structure
Ironworkers await the final beam – 3月. 7, 2024
一个穿着安全夹克、戴着安全帽的人向前倾着身子,在一根涂成白色的钢梁上写字
项目经理 保罗•怀特岛 signs the final beam – 3月. 7, 2024
一个矮个子和一个高个子穿着施工安全背心,戴着安全帽,站在涂成白色的钢梁前. handwriting on the beam says "thank you SPS voters, Julia Pearson"
蒙特莱克校长茱莉亚·皮尔森和资本项目和设施总监理查德·贝斯特在beam签约仪式上. 7, 2024
两个人站在钢架结构的一个角落的红、白、蓝三色梁上. 他们在握手. 一端是常青树,另一端是美国国旗.
Congratulatory handshake on placement of final beam – 3月. 7, 2024
2 people on top of a steel structure on each side of a red, 白色和蓝色的横梁上有一面美国国旗和一棵常青树
Ironworkers bring the beam into place – 3月. 7, 2024
一根钢梁正被吊车吊到钢架建筑的顶部 . Two people wait on top of the existing structure
Flying in the final beam – 3月. 7, 2024
一群穿着建筑安全背心和帽子的人站在钢梁前,后面是钢框架结构
Project crew with the final beam – 3月. 7, 2024

Watch the video of the final steel beam being put into place.

视频直播

相机1

照相机2

建筑的照片

a two story brick building has windows on the top floor. 挖掘机正停在它下面的水泥地上,水泥地只剩下两面墙. a dumpster is next to the concrete
拆除附属于地标建筑的旧体育馆- 2023年8月
a two story brick building has had something removed over a concrete pad
Existing outdoor play area demolition in progress – August 2023
a brick building with construction in progress on the outside
Shoring the existing west side of the school – Sept. 2023
a construction site with material on the ground
Excavation on the south side of the building – Sept. 2023
aerial view of a construction site next to a building
2023年10月鸟瞰图
砖房的窗孔和旁边的建筑都是用木头做的
Concrete forms and rebar for new footing next to historic building – Oct. 2023
这是一幢部分被拆毁的建筑,柱子和横梁被木头覆盖,一些窗户开着
Interior demolition on the first floor of the landmarked building – Oct. 2023
建筑工地鸟瞰图,一端是砖砌建筑,四周是街道
Project view with excavation in process, looking northwest – Nov. 2023
rebar trench next to a brick building
Concrete form work and rebar placement for new footing – Nov. 2023
建筑工地的鸟瞰图,一端是砖房,远处是一个湖
Aerial site view looking northwest – Dec. 2023
一座砖房,窗户用木板封住,坐落在一个建筑工地上,前面是一堵混凝土墙
Concrete retaining wall complete on west side of historic building – Dec. 2023
一个建筑工地有一辆混凝土泵车在一个表格中安装混凝土
Placing concrete stem wall, looking west – Dec. 2023
挖掘机在泥土上挖了一条沟渠,沟渠有宽的混凝土形式,有钢筋和混凝土泵喷嘴.
Pumping concrete into concrete footing forms with rebar – Dec. 2023
建筑工地的鸟瞰图,周围是街道和房屋,远处有一个湖和一个体育场
Looking north with Husky Stadium in background – Feb. 2024
航拍图显示一座矩形砖砌建筑,后面正在施工,包括一台起重机
向东望去,前方是标志性建筑,后方是正在建设中的新钢结构建筑. 2024
一座三层建筑的钢框架,前景部分显示了起重机
Steel erection for the new addition – Feb. 2024
一间长长的房间,露出椽子,几扇窗户旁边有一面水泥墙
地标建筑抗震升级的混凝土剪力墙- 2月. 2024

建设更新

Progress updates are posted for the previous month.

202年3月主要活动4  

  • Completed structural steel for the addition.
  • Poured the concrete for the learning terrace.
  • Continued to modernize the landmarked building.

Major activity expected in April 2024

  • Begin construction of the new gymnasium building.
  • Start putting the roof on the new building.
  • Continue work on the landmarked building.
  • Continue framing the outside of the new building.

In May, the crane will return for some additional construction work.

Read the Neighborhood News Update

当前的设计

These images show architect’s drawings of how the new school might look.

建筑师设计的一个大的室内空间,有一个舞台和一些圆桌
Potential view of the commons and stage-Oct 2022
a site plan drawing of a u-shaped building with a courtyard
Site plan for proposed addition and existing building – Oct. 2022
architect's drawing of a brick building with a side walk and garden
Architect’s drawing of the new entrance – June 2023
建筑师绘制的带有庭院和操场设备的砖砌建筑
Architect’s drawing of play area – June 2023

社区参与

Virtual community update — December 2022

Thank you to everyone who joined us on Tuesday, Dec. 13.

Community Meeting Presentation

You can always submit additional questions to 大家一起说. 选择Montlake Construction,以确保直接提供给Montlake项目团队.

School Design Advisory Team (SDAT)

在设计过程的早期, 来自学校社区的代表聚集在一起,形成学校的SDAT. sdat通常包括学校和地区的工作人员、家长和社区成员. 学生 are sometimes included for all or part of the process. The project construction managers also take part. Learn more about the 蒙特莱克小学 SDAT.

Virtual Community Meeting – June 2022

感谢所有能在6月2日星期四加入我们的社区更新的人.

Community Update Presentation2022年6月

项目简介

The 2-story existing school building is a designated Seattle Landmark. 这座22,447平方英尺的标志性建筑将进行翻新和现代化改造.

拟议的设计包括对现有地标建筑的翻新和新建3层建筑.

Designed for current and future 学生

一旦完成, 学校将为500名K-5小学生提供公平的学习空间. 它将符合地区教育标准,同时反映由学校领导组成的学校设计顾问团队的意见, 学生, 父母, 社区成员.

扩建部分将设置在场地上,其屋顶高度尊重当前学校建筑和社区的规模.

  • 无障碍设施将建在整个校园,以确保每个人都能参加或参观学校.
  • 教室将安排各种共享学习空间,以支持每个学生的学业成功.

安全与保障

学生, 家庭, 游客将通过新增建筑东北侧的新入口广场进入.

Visitors will enter through a single access point, 在进入学校之前,安全的主入口邀请他们进入行政办公室办理登记手续.

室外连接

新的户外学习空间将建在标志性学校建筑的东侧. 中央游戏庭院将提供与花园露台的直接连接. 二楼的学习和游戏平台将直接连接到教室.

Building a sustainable future

Sustainable design features will be built in to work toward the
district goals for clean energy and renewable resources, 包括高性能的建筑围护结构和太阳能电池板的安装.

Temporary Move — 2023-24 and 2024-25 School Years

蒙特莱克小学将搬到约翰·马歇尔学校的临时地点, 520 NE Ravenna Blvd, 在施工期间. School bus transportation will be provided.

更多的信息

设计公司: 经销商集团

General Contractor/Construction Management Firm (GC/CM): 在建

项目预算: $64.800万年

资金来源: 建筑卓越V (BEX V)资本税,于2019年由西雅图选民批准.

项目经理保罗·怀特, pdwight@lfkgw.com, 206-252-0648